Timetable for Lime Walk, 3 January to end February 2017

14/12/2016

Please note that this timetable could change if work is delayed for any reason.  Should this be the case, a new timetable will be issued as soon as possible. The route of the pipe should not alter.

From 3 January, Lime Walk will be one-way from Old Road down to the All Saints Junction (chicane).

Looking north from Old Road down towards the chicane, the trench will be along the right side of the street (in front of the houses with odd numbers) and traffic will pass on the left (in front of the houses with even numbers).

During each phase of works, there will be no access to odd numbers' driveways. Access will be resumed when the phase moves on. Pavements will be kept open.

Access to even numbers' driveways will be open at all times.

Pavements on both sides of the road will be kept open at all times.

There will be a drop off zone at each end of the trench. 24-hour security staff can assist with deliveries or access for disabled.

Phase 1:  3 - 20 January 2017

Street parking between house numbers 73 - 108 suspended.  

Phase 2: 23 January - 10 February 2017

Street parking between house numbers 104 - 126 suspended. 

Phase 3: 13 - 24 February 2017

Street parking between house numbers 125 - 134 suspended.  

If you disabled or need assistance with access, please contact hospitalenergyproject@ouh.nhs.uk and a Vital Energi project coordinator will come and discuss your needs.